Construction Update – August 2023
The main roads are paved in the first phase! It’s exciting to see the roundabout take shape and roads now lead the way to the future first park, builder models, elementary school and Midtown Mayfair.
DNT will finish this phase of construction on the main roads by early September, and CC Carlton plans to begin laying base for the first neighborhood next month with paving slated for early November. DNT will then gear up for construction to begin in September on the second neighborhood of homes.
5 Star is now clearing the way for the community’s Waste Water Treatment Facility on the eastern border with the Cloacina plant estimated to arrive in November. Southstar and J&A Wastewater are overseeing this effort and coordinating electrical, structural and civil engineering as well as construction by 5 Star.
A new regional storm facility is well underway by D&D Construction with completion of the dam expected for November.
And an exciting highlight for future home and business owners – Centric Gas and Fiber contractors are now onsite installing natural gas lines and high-speed fiber for the Mayfair community!
This all leads the way for builders to begin new home construction in early 2024 with models expected in late Spring/early Summer.
Watch it all take shape.